What course of action is the best to avoid scenarios where the client asks for changes after the project has commenced?
1) Demand extra payment for the changes.
2) Ignore the client's messages requesting the changes.
3) Insist that out of scope work would not be done.
4) Communicate the conditions under which change requests would be entertained.