Big Kola Company has been concerned that specialized fruit drinks have been eroding their cola market. The CEO mandates that "If you can’t beat them, join them." Grape juice was the first product that was successful after an advertising blitz claiming the antitoxin benefits. Lately, competition is compressing grape juice margins and profits. Months of additional market surveys and focus groups have resulted in three potential high-margin drinks: cranberry, blueberry, and pomegranate. All these choices represent antitoxins. The decision is to produce the pomegranate drink that has many health claims. For example, the relative ability of these juices to eliminate harmful free radicals (antitoxins) is 71 percent for pomegranate, 33 percent for blueberry, and 20 percent for cranberry (Technion Institute of Technology). The market potential appears very attractive and should have a higher profit margin than the other potential juice products. Another appeal for pomegranate juice is its familiarity in the Middle East and Asia. The Priority Matrix for the POM1 Project is:
Time Scope Cost
Constrain X
Enhance X
Accept X
* Cliff Gray, Erik Larson, & Pinyarat Sirisomboonsuk, doctoral candidate at Rawls College of Business, Texas Tech University.
625
626 Appendix 2 Computer Project Exercises
Connor Gage, the project manager, has formed his project team and the members have come up with the following work breakdown structure.
1.0 POM1Project
1.1 R&D product development
1.1.1 Need survey
1.1.2 Set product specs
1.1.3 Shelf life report
1.1.4 Nutrition report
1.2 Secure fruit suppliers
1.3 Initial Production
1.3.1 Equipment rehab
1.3.2 Production trials
1.3.3 Quality trials
1.3.4 Quality metrics
1.3.5 Quality training
1.4 Distribution
1.4.1 Market testing
1.4.2 Package design
1.4.3 Select distributors
1.5 Legal
1.5.1 Complete FDA certification
1.5.2 Register trademark
1.6 Prepare product launch
Part 1
Develop the WBS outline using the software available (save your file).
Use this file and the information provided below to create a project schedule.
The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26. (USE 2016 CALENDAR YEAR IN PROJECT LIBRE)
If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given off.
The project team works eight-hour days, Monday through Friday.
The project will begin on Dec. 1, 2015.
Based on this schedule, submit a memo that answers the following questions:
W hen is the project estimated to be completed? How many working days will it take?
What is the critical path?
Which activity has the most total slack?
How sensitive is this network?
Identify two sensible milestones and explain your choice.
Appendix 2 Computer Project Exercises 627
Include the following (one page) printouts:
A Gantt chart.
A network diagram highlighting the critical path.
A schedule table reporting ES, LS, EF, LF, and slack for each activity.
Hints: Change the timescale to months and weeks. The estimated duration of the project is 135 days.
Remember: Save your files for future exercises!
The following information has been derived from the WBS. Note that the activity number is what appears in the software with the complete WBS entered.
#* Activity Duration Predecessor(s)
3 Need survey 20 None
4 Set product specs 15 3
5 Shelf life report 10 4
6 Nutrition report 5 4
7 Select fruit suppliers 20 5, 6
9 Equipment rehab 30 4
10 Production trials 15 7, 9
11 Quality trials 20 10
12 Quality metrics 5 11
13 Quality training 15 12
15 Market testing 30 5, 6
16 Package design 15 15
17 Select distributors 25 5, 6
19 Complete FDA certification 15 7, 15
20 Register trademark 5 7, 15
21 Prepare product launch 15 13, 16, 17, 19FS 1 25 days, 20FS 1 15 days
FS = Finish to Start lag