Seven jobs are available to be produced on a single machine. The jobs have processing times (2, 1, 5, 3, 9, 13, 24) and due dates (12, 34, 8, 42, 65, 51, 29), respectively. Find the schedule that minimizes average flow time. What is the minimized average flow time?