A project manager is assigned to a project team midway through execution Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes What should the project manager do first?
• Consult the communications management plan
• Escalate the issue to the product owner
• Convene an impact analys's meeting
• Review the stakehoider register