As a project manager, you encounter a problem that will affect the project delivery date. You need to raise the issue to project stakeholders. How should you best communicate the problem to stakeholders?
a. Email stakeholders outlining the problem in detail and ask how they would like to proceed.
b. Provide stakeholders with a short summary and proposed solution to the problem.
c. Add stakeholders to an ongoing email chain to provide them with context for the problem.