Senior managers review the criteria at each gate to make a decision in stage-gate systems. Which of the following is not among the four decisions they make?
1) Approve the project to proceed to the next stage
2) Reject the project and terminate it
3) Put the project on hold and re-evaluate it later
4) Delegate the decision to a lower-level manager