For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Activity duration is 4 days. Which of the following statements is true?
A) The Late Finish is 14
B) The Early Finish is 12
C) Delaying this activity by 2 days will not affect project duration
D) A and B E) A, B, and C