A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval. What should the project manager have done to avoid this setback?
a. Analyzed stakeholders
b. Developed benchmarking
c. Detailed the project charter
d. Assessed feasibility and impacts