To allocate resources for resource-constrained projects, project managers may perform the following activities EXCEPT:
a. Constrained to level within available slack times
b. Prioritizing activities based on slack times
c. Delaying activities with slack times
d. Delaying activities without slack times
e. Applying the parallel method in scheduling