There are three scenarios for a project. The Best Case scenario has a Net Present Value ("NPV") of $20,000 and probability of 30%. The Base Case scenario shows a NPV of $1,000 and probability of 45%. The Worst Case scenario has a NPV of negative $5,000 and a probability of 25%. What is the project's Coefficient of Variation?

A.1.60
B.1.71
C.1.92
D.1.80