The work breakdown structure is an important tool used by the project manager and the project team for all of the following reasons except:
a. Improved communication
b. Displays dependencies for project activities
c. Improves accuracy of cost and duration estimates
d. Identifies major project deliverables
e. Provides a basis for generating the project plan



Answer :