Which of the following is not a possible output of the Estimate Costs process?
(Hint: Consult the PMBOK Guide, Sixth Edition, although you should be able to derive the answer from the lectures.)
a. Activity cost estimates
b. Basis of estimates
c. The project's cost baseline
d. Risk register updates