Recently the team has noted an issue that was slowed down the work progress if not block progress completely one team member was quick to enter the issue into the issue log and now the team is looking to the project manager for direction on what to do next you as a project manager would indicate to move forward next week.

a. giving feasible date that the project team can deliver a solution.
b. monitoring the issue and reporting on it at status meetings to the team
c. assigning an individual who will be responsible from this point forward until a workaround is developed.
d. escalating the leading to the project owner or sponsor for feedbac