Qpaoswp93871 Qpaoswp93871 10-06-2024 Business Answered If an activity's progress is defined as 0% until the activity is complete, the project manager is using:a. The 50/50 ruleb. The all or nothing rulec. The 0/100 ruled. The Do Not Pass Go rule