A project integrates with several systems developed by various vendors and one of these vendors has gone out of business. What should the project manager do first?
A. Meet with this vendor to identify a replacement.
B. Review the risk register and update the issue log.
C. Calculate the delay and notify the project sponsor of the new timeline.
D. Negotiate with another vendor to produce the deliverable.