You are considering two mutually exclusive projects, projects A and B. The crossover point of the NPV profiles for these projects occurs in the first quadrant. The cost of capital is equal to the IRR of "A - B" cash flows. What should your accept decision be?
Multiple choice question.
Accept either project A or B, but not both
Accept project B and reject project A
Accept project A and reject project B
Reject both project A and B