A scrum teams is finding it difficult to get work done since team members are distracted by being pulled away to take care of work requested by other teams. The team has been regularly failling to deliver on their sprint goals. As a manager, if the scrum team asks you for help, what should you do to solve this problem? - Two answer

A. Ask for more people on the team to compensate fort he interruptions
B. Coach the scrum team to the more conservative in defining their sprint goal, to account for the time team mebers will need to spend doing other work
C. Extend the lenght of a sprint if they need more time to complete the sprint goal
D. Work with the scrum team and other teams to find ways to re-assign the interrupting work to people outside of the scrum team
E. Make their sprints longer to account for the interruptions.