In the agile project management approach:
a. Monitoring risks is likely to be performed within an iteration/sprint.
b. Monitoring risks happens immediately after an iteration/sprint ends.
c. Monitoring risks could result in changes to the product backlog.
d. Monitoring risks is done during the iteration/sprint daily standup.