The Air Force is procuring maintenance services, and the Contracting Officer decides that no discussions are required to select the best contractor. However, the contractor's proposal has a typographical error showing period of performance beginning 1 June rather than 1 July. What type of information exchange would be used to resolve this discrepancy?
A.Negotiations
B.Communications
C.Clarifications
D.Solicitations