A project manager is about to start the process of identifying quality requirements and standards for an infrastructure project. The project manager examines the project charter to gain a high-level understanding of project objectives and reviews relevant information from the available components of the project management plan.
What else should the project manager do to gather inputs to the process?
o Conduct a brainstorming session with the project team and subject matter experts to develop the quality management plan
o Perform a cost-benefit analysis to determine if the planned quality activities are cost-effective
o Update the lessons learned register with information on challenges encountered in the quality planning process
o Review the requirements documentation to gain an understanding of the project and product quality requirements