To control noise, work hours may be agreed upon to reduce noise-related problems. This would affect:

A. Scheduling, which may increase costs and therefore the contract amount.
B. Productivity, which may increase costs and therefore the contract amount.
C. Material delivery, which may increase costs and therefore the contract amount.



Answer :

Final answer:

Agreeing on work hours to control noise can impact productivity and contract amounts.


Explanation:

Productivity would be affected by agreeing upon work hours to control noise, potentially increasing costs. This could lead to adjustments in work schedules impacting the efficiency of operations.

For example, changing from a five-day workweek to four extended work days may be proposed to increase productivity and save on building maintenance and utility costs.

Management decisions related to work hours can have financial implications on contract amounts due to potential shifts in productivity and operational efficiency.


Learn more about Effect of work hours on productivity and costs here:

https://brainly.com/question/34609717