Which project lifecycle allows only a single delivery?

A. Functional
B. Incremental
C. None of the above
D. Predictive



Answer :

Final answer:

The Predictive project lifecycle allows only one delivery, with predetermined scope, cost, and timeline.


Explanation:

Predictive project lifecycle allows only a single delivery. In this approach, the project scope, cost, and timeline are determined at the beginning, and the final product is delivered all at once upon completion.