Current Attempt in Progress

Don Lieberman and Associates, a CPA firm, uses job order costing to capture the costs of its audit jobs. There were no audit jobs in process at the beginning of November. Listed below are data concerning the three audit jobs worked on during November.

\begin{tabular}{|c|c|c|c|}
\hline
& Sunland Inc. & Carla Vista Inc. & Sandhill Inc. \\
\hline
Direct materials & [tex]$\$[/tex] 610[tex]$ & $[/tex]\[tex]$ 480$[/tex] & [tex]$\$[/tex] 300[tex]$ \\
\hline
Auditor labor costs & $[/tex]\[tex]$ 6,300$[/tex] & [tex]$\$[/tex] 7,600[tex]$ & $[/tex]\[tex]$ 3,575$[/tex] \\
\hline
Auditor hours & 76 & 90 & 48 \\
\hline
\end{tabular}

Overhead costs are applied to jobs on the basis of auditor hours, and the predetermined overhead rate is [tex]$\$[/tex] 55[tex]$ per auditor hour. The Sunland Inc. job is the only incomplete job at the end of November. Actual overhead for the month was $[/tex]\[tex]$ 13,900$[/tex].

(a) Determine the cost of each job.
- Sunland Inc.: [tex]$\square$[/tex]
- Carla Vista Inc.: [tex]$\square$[/tex]
- Sandhill Inc.: [tex]$\square$[/tex]



Answer :

To determine the cost of each job, we'll follow these steps for each audit job: Sunland Inc., Carla Vista Inc., and Sandhill Inc. We'll calculate the total cost by adding the direct materials, the auditor labor costs, and the overhead costs. Overhead costs are calculated using the given predetermined overhead rate and the number of auditor hours for each job.

### Step-by-step Solution:

1. Determine Overhead Costs:
- The predetermined overhead rate is [tex]$55 per auditor hour. 2. Calculate the Overhead Cost for Each Job: - Sunland Inc. - Auditor hours: 76 - Overhead cost for Sunland = \( 76 \text{ hours} \times \$[/tex]55/\text{hour} = \[tex]$4,180 \) - Carla Vista Inc. - Auditor hours: 90 - Overhead cost for Carla Vista = \( 90 \text{ hours} \times \$[/tex]55/\text{hour} = \[tex]$4,950 \) - Sandhill Inc. - Auditor hours: 48 - Overhead cost for Sandhill = \( 48 \text{ hours} \times \$[/tex]55/\text{hour} = \[tex]$2,640 \) 3. Calculate the Total Cost for Each Job by Adding Direct Materials, Auditor Labor Costs, and Overhead Costs: - Sunland Inc. - Direct materials: $[/tex]610
- Auditor labor costs: [tex]$6,300 - Overhead cost: $[/tex]4,180
- Total cost for Sunland = [tex]\( \$610 + \$6,300 + \$4,180 = \$11,090 \)[/tex]

- Carla Vista Inc.
- Direct materials: [tex]$480 - Auditor labor costs: $[/tex]7,600
- Overhead cost: [tex]$4,950 - Total cost for Carla Vista = \( \$[/tex]480 + \[tex]$7,600 + \$[/tex]4,950 = \[tex]$13,030 \) - Sandhill Inc. - Direct materials: $[/tex]300
- Auditor labor costs: [tex]$3,575 - Overhead cost: $[/tex]2,640
- Total cost for Sandhill = [tex]\( \$300 + \$3,575 + \$2,640 = \$6,515 \)[/tex]

### Final Costs:
- Sunland Inc.: [tex]$11,090 - Carla Vista Inc.: $[/tex]13,030
- Sandhill Inc.: $6,515

This completes the detailed computation of the costs for each job.