16. A contractor agrees to lay a road 3000 m in 30 days. 50 men are employed, and they work for 8 hours per day. After 20 working days, he finds that only 1200 m of the road is completed.

(a) How many more men does he need to employ to finish the project on time if each man continues to work 8 hours a day?

(b) How many more men does he need to employ to finish the project on time if each man now works 10 hours a day?



Answer :

Sure! Let's address each part of the question systematically, step by step.

### Part (a): Determining the number of additional men needed if working 8 hours per day

Firstly, we know from the question the following information:
- Total length of the road to be laid: 3000 meters
- Total time to lay the road: 30 days
- Initial number of men employed: 50 men
- Initial working hours per day: 8 hours per day
- Length of the road completed after 20 days: 1200 meters

#### Step 1: Calculate the remaining road length

First, we determine the amount of road left to be constructed after 20 days:

[tex]\[ \text{Remaining road length} = \text{Total road length} - \text{Road completed} = 3000 \text{ m} - 1200 \text{ m} = 1800 \text{ m} \][/tex]

#### Step 2: Calculate the remaining days

Next, we calculate the days left to complete the road:

[tex]\[ \text{Remaining days} = \text{Total days} - \text{Days passed} = 30 \text{ days} - 20 \text{ days} = 10 \text{ days} \][/tex]

#### Step 3: Calculate the initial work rate (road laying rate)

To understand the pace at which the initial team worked, we calculate the road laying rate:
[tex]\[ \text{Total man-hours in the first part} = \text{Initial men} \times \text{Initial hours per day} \times \text{Days passed} = 50 \text{ men} \times 8 \text{ hours/day} \times 20 \text{ days} = 8000 \text{ man-hours} \][/tex]

[tex]\[ \text{Road laying rate} = \frac{\text{Total road laid}}{\text{Total man-hours in first part}} = \frac{1200 \text{ m}}{8000 \text{ man-hours}} = 0.15 \text{ meters/man-hour} \][/tex]

#### Step 4: Calculate required man-hours to finish the remaining road

Now, calculate the required man-hours to complete the rest of the road:
[tex]\[ \text{Required man-hours for remaining road} = \frac{\text{Remaining road length}}{\text{Road laying rate}} = \frac{1800 \text{ m}}{0.15 \text{ meters/man-hour}} = 12000 \text{ man-hours} \][/tex]

#### Step 5: Calculate the number of men needed, working 8 hours per day

Finally, determine the number of men required to finish the road in the remaining 10 days, working 8 hours per day:

[tex]\[ \text{Required men} = \frac{\text{Required man-hours}}{\text{Remaining days} \times \text{Hours per day}} = \frac{12000 \text{ man-hours}}{10 \text{ days} \times 8 \text{ hours/day}} = 150 \text{ men} \][/tex]

Since initially there were 50 men, the additional number of men needed is:

[tex]\[ \text{Additional men needed} = 150 - 50 = 100 \text{ men} \][/tex]

### Part (b): Determining the number of men needed if working 10 hours per day

#### Step 1: Calculate the number of men needed, working 10 hours per day

Using the previously calculated required man-hours (12000 man-hours) and the remaining days (10 days), we determine how many men are needed if they now work 10 hours a day:

[tex]\[ \text{Required men} = \frac{\text{Required man-hours}}{\text{Remaining days} \times \text{New hours per day}} = \frac{12000 \text{ man-hours}}{10 \text{ days} \times 10 \text{ hours/day}} = 120 \text{ men} \][/tex]

Since initially there were 50 men, the additional number of men needed is:

[tex]\[ \text{Additional men needed} = 120 - 50 = 70 \text{ men} \][/tex]

Summary:
(a) The contractor needs to employ 100 additional men if working 8 hours per day.
(b) The contractor needs to employ 70 additional men if working 10 hours per day.