Suppose that the necessary activities to implement the project of renovating the drainage networks of the rainwater in Alexandria are in accordance with the following schedule:

1. Draw the PERT Network.
2. Clarify the critical path.
3. What is the expected completion time for the project?
4. Which is the activity with the largest slack time?



Answer :

Final answer:

The PERT Network is used to visualize project activities and dependencies. The critical path ensures timely project completion. The expected completion time and slack times are crucial project management metrics.


Explanation:

PERT Network for Renovating Drainage Networks in Alexandria:

A PERT chart is created to show the activities of the project and their dependencies. Each activity is represented by a node, and arrows between nodes indicate the sequence of activities.

Critical Path:

The critical path is the longest sequence of activities that must be completed on time to prevent delays in project completion.

Expected Completion Time and Activity with Largest Slack Time:

The expected completion time is the total time required to finish all project activities. The activity with the largest slack time is the one with the most flexibility in its start time without delaying the project.


Learn more about Project Management here: