Use the table as a guide. Prepare a budget for your mining headgear.

Note: Some of the given prices are not realistic.

BUDGET

\begin{tabular}{|l|l|l|l|}
\hline
Labour Costs & Cost per Day & Number of Days & Total Cost \\
\hline
Architect & R825.30 & 3 & R2475.90 \\
\hline
Engineers-Structural & R836.80 & & \\
\hline
Welders & R588.00 & & \\
\hline
Bricklayers & R353.95 & & \\
\hline
Fitter and Turner & R983.00 & & \\
\hline
Unskilled Labour & R202.85 & & \\
\hline
Accountants & R1320.00 & & \\
\hline
Office Staff & R412.50 & & \\
\hline
Volunteers & R238.99 & & \\
\hline
Total for Labour & & & \\
\hline
\end{tabular}



Answer :

To prepare the budget for the mining headgear, let's complete the table based on the given information:

[tex]\[ \begin{tabular}{|l|l|l|l|} \hline \textbf{Labour costs} & \textbf{Cost per day} & \textbf{Number of days} & \textbf{Cost} \\ \hline Architect & R825,30 & 3 & R2475,90 \\ \hline Engineers- Structural & \mbox{R836,80} & 3 & R2510,40 \\ \hline Welders & \mbox{R588,00} & 3 & R1764,00 \\ \hline Bricklayers & R353,95 & 3 & R1061,85 \\ \hline Fitter and turner & R983,00 & 3 & R2949,00 \\ \hline Unskilled labour & R202,85 & 3 & R608,55 \\ \hline Accountants & R1320,00 & 3 & R3960,00 \\ \hline Office staff & R412,50 & 3 & R1237,50 \\ \hline Volunteers & R238,99 & 3 & R716,97 \\ \hline \textbf{Total for labour} & & & \textbf{R17284,17} \\ \hline \end{tabular} \][/tex]

### Detailed Breakdown:

1. Architect:
- Cost per day: R825,30
- Number of days: 3
- Total cost: R825,30 3 = R2475,90

2. Engineers- Structural:
- Cost per day: R836,80
- Number of days: 3
- Total cost: R836,80
3 = R2510,40

3. Welders:
- Cost per day: R588,00
- Number of days: 3
- Total cost: R588,00 3 = R1764,00

4. Bricklayers:
- Cost per day: R353,95
- Number of days: 3
- Total cost: R353,95
3 = R1061,85

5. Fitter and Turner:
- Cost per day: R983,00
- Number of days: 3
- Total cost: R983,00 3 = R2949,00

6. Unskilled Labour:
- Cost per day: R202,85
- Number of days: 3
- Total cost: R202,85
3 = R608,55

7. Accountants:
- Cost per day: R1320,00
- Number of days: 3
- Total cost: R1320,00 3 = R3960,00

8. Office Staff:
- Cost per day: R412,50
- Number of days: 3
- Total cost: R412,50
3 = R1237,50

9. Volunteers:
- Cost per day: R238,99
- Number of days: 3
- Total cost: R238,99 * 3 = R716,97

### Total Labour Cost Calculation:
Adding all the individual costs together:
[tex]\[ 2475,90 + 2510,40 + 1764,00 + 1061,85 + 2949,00 + 608,55 + 3960,00 + 1237,50 + 716,97 = R17284,17 \][/tex]

Thus, the total budget for labour costs is R17284,17.