A change request in this scenario should authorize team overtime, additional resources using the contingency fund, and corrective action based on causes.
When a project manager realizes that only 75% of the work has been completed and an accepted deadline is approaching, issuing a change request is crucial. The change request should authorize team overtime to meet the schedule as it provides the opportunity to catch up on the remaining work and ensure project completion on time.
Authorizing additional resources using the contingency fund could also be necessary to support the increased effort required to complete the project within the deadline. It's essential to consider corrective action based on causes to address any underlying issues affecting the project progress.
https://brainly.com/question/45865785