You are creating a database for the Oklahoma City Thunder NBA basketball team. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project.
Please find these values
What are the critical activities?
What is the slack for C?
What is the slack for D?
What is the slack for E?
What is the slack for F?
What is the length of the project?