Which of the following activities is NOT included in the Monitor and Control Risk process?

A. Determining the need to execute contingency or fall-back plans.
B. Reviewing risk response actions and their effectiveness for risks that are underway.
C. Implementing risk responses for identified risks.
D. Watching for new risks.



Answer :

Final answer:

The Monitor and Control Risk process does not include implementing risk responses.


Explanation:

Implementing risk responses for identified risks is NOT included in the Monitor and Control Risk process. This process focuses on monitoring and controlling risks, which involves reviewing risk response actions, determining the need for contingency plans, watching for new risks, but implementing risk responses is a separate process.


Learn more about Risk Management here:

https://brainly.com/question/43481450