Answer :

Let's analyze and solve the problem step by step:

1. Work Done Yesterday:
Mohit did [tex]\(\frac{2}{6}\)[/tex] of the work yesterday. This can be simplified to:
[tex]\[ \frac{2}{6} = \frac{1}{3} \approx 0.3333 \][/tex]

2. Work Done Today:
Mohit also did [tex]\(\frac{2}{6}\)[/tex] of the work today. Similarly:
[tex]\[ \frac{2}{6} = \frac{1}{3} \approx 0.3333 \][/tex]

3. Total Work Done So Far:
To find the total work done by Mohit so far, we add the work he did yesterday and the work he did today:
[tex]\[ \text{Total work done} = \frac{1}{3} + \frac{1}{3} = \frac{2}{3} \approx 0.6666 \][/tex]

4. Remaining Work:
The total work required to complete the task is 1 (which represents 100% of the work). We need to find out how much work is left.
[tex]\[ \text{Remaining work} = 1 - \text{Total work done} = 1 - \frac{2}{3} = \frac{1}{3} \approx 0.3333 \][/tex]

So, Mohit has approximately [tex]\( \frac{1}{3} \approx 0.3333 \)[/tex] of the work left to complete tomorrow.

Answer:

[tex]\frac{1}{3}[/tex]

Step-by-step explanation:

Lets break down the problem step by step:

1. Total work to be done: assume the total of work is represented by 1 unit

2. work done yesterday; Mohit did [tex]\frac{2}{6\\ }[/tex] of the work yesterday.

3. work done today: Mohit di [tex]\frac{2}{6}[/tex] of the work today

4. Total work done so far; Add the fractions of work done yesterday and today:

[tex]\frac{2}{6} + \frac{2}{6} = \frac{4}{6}[/tex]

= [tex]\frac{2}{3}[/tex]

5. Subtract the work done so far from total work:

[tex]1 - \frac{2}{3} = \frac{3}{3} - \frac{2}{3} = \frac{1}{3}[/tex]

So, Mohit needs to do [tex]\frac{1}{3}[/tex] of the work tomorrow to complete the remaining work.